Coca-Cola HBC

725 tons
CO2 reduction
back to project page

Coca-Cola HBC

Roof system

Coca-Cola HBC Austria was founded in 1929. It is one of the biggest companies in the non-alcoholic beverage industry in the country, and is a franchised bottler of The Coca-Cola Company. More than 6o different beverages are produced for the Austrian market in the state-of-the-art production and logistics center in Edelstal (Burgenland).

 

Sustainability is an integral part of the corporate philosophy. The company is actively working to reduce the environmental footprint of the production, transportation and cooling equipment. The Selina PV-experts and the sustainability team of Coca-Cola HBC have planned a 2,8 MW PV-system.

The construction work started in February 2019, and the commissioning of the plant happened in May 2019.

The plant saves about 725 tonns of CO2 emissions per year. The project was realized in co-operation with our operating company SolPV.

 

Technical Data

  • Location: Burgenland
  • Output: 2,858.00 kWp
  • Annual yield: 2,924 MWh
  • CO2 reduction: 725 tons
  • Module surface: 14,960 m²
  • Modules: 9,200 á 310W
  • Inverter: Huawei
  • Put into operation: 25/05/2019
  • Electricity generation corresponds to: 600 households
  • Subsidy: OeMAG